[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index] [Wg-test-framework] Test project costings
I promised to send a worked-out costing for going with Jump.
Things which need to be included:
Hosting in a proper datacentre[0]
Space charges[1]
Power charges
External internet connection (at least one
for each infrastructure server) [2]
Bandwidth charges [3]
Intra-rack connectivity if expand to multiple racks
Physical rack cabinet
PDU-controlled socket for each machine
Backups[4]
Remote serial console access to infrastructure servers
Sysadmin on contract basis
Assumptions:
Space and power:
2 infrastructure servers at 2U and 200VA (~=200W) each
24 test servers at 1U and 200VA each
1 internal switch at 1U, 100VA
1 external switch at 1U, 100VA
For a total of 30U, 5400VA
Bandwidth:
Total external 4Mbit/s 95%ile.
Contract sysadmin
80h setup over two weeks, one week spent onsite
5h per week ongoing
Things NOT included:
Servers, testbed systems
Internal switches
Internal CAT-45 wiring
Multi-port serial boards
Serial leads
The proposal would involve the following invoice line items from Jump:
* "Standard colo" total power 5300VA (we don't need to budget
for the external switch): L3975/month, no setup fee.
* "iSCSI" backup storage one 1Tb unit: L25/month, no setup fee.
* Consultancy L50/hr, 80h setup, 5h ongoing: L5000 setup, L1083/month.
* Consultancy mileage: 5x Cambridge to London (60mi) and back
ie 500mi at 0.40: L200.
Bottom line:
Total L5083/month, L5200 setup. At the current exchange rate of
US$1 = UKL0.58392, that's $2968/month, $3036 setup.
Notes:
The power budget above is probably an overestimate, perhaps by a
factor of two or so, so the bottom line I have quoted is a maximum.
Jump have said that they if we commit to 2000VA at their current
prices for a 3-year term, they can offer us a dedicated rack. If we
don't have certainty of funding for a 3-year term we can probably
negotiate a shorter term with a higher commitment.
Ian.
[0] In this case, Telehouse in London Docklands
[1] Jump do not actually charge separately for space.
[2] Jump actually offer two connections per server.
[3] Jump bundle 4Mbit/s 95%ile _per server.
[4] I have costed this based on backups of the infrastructure servers
being done to Jump's iSCSI facility, with the machinery on our
servers set up on a consultancy basis by Jump.
_______________________________________________
Wg-test-framework mailing list
Wg-test-framework@xxxxxxxxxxxxxxxxxxxx
http://lists.xenproject.org/cgi-bin/mailman/listinfo/wg-test-framework
|
![]() |
Lists.xenproject.org is hosted with RackSpace, monitoring our |